Rex targets February 2026 to trigger Benin well production

The installation of reservoir screens and pumps remain for final stages.

Rex International Holding said its indirect subsidiary, Akrake Petroleum Benin, is finishing drilling at the AK-2H production well in the Sèmè Field, offshore Benin.

The well is expected to begin production in the first week of February.

Completion work includes installing reservoir screens and a downhole electrical submersible pump.

In addition to the well completion, the mobile offshore production unit Stella Energy 1 and the floating storage and offloading unit Kristina are also in the final stages of installation.

Rex did not disclose expected output from the well.
 

Join Singapore Business Review community
A NOTE FROM SINGAPORE BUSINESS REVIEW

If you've been wondering whether SBR could work for your company — yes, probably.

A lot of the companies we partner with started as readers. They'd been following our coverage for a while, saw their own customers and competitors in it, and eventually asked the obvious question: could we do something with you? The answer is usually yes. The shape of it depends on what you're trying to do.


The options are broader than most people assume — thought leadership articles, sponsored content, industry summits across Southeast Asia, regional awards programmes, podcasts, and media placements in print and digital. Some partners use one channel; most use a mix. We figure out the right combination by starting with your brief, not with our rate card.


So if the question has been on your mind, here's the easy way to ask it.

We'll tell you honestly whether we can help, and how. It's a better use of everyone's time.